Updating Results

McConnell Dowell

  • 500 - 1,000 employees

Ashlee Othen

Graduate Engineer at McConnell Dowell

Bachelor of Engineering (Honours) (Mechanical Engineering) at University of Adelaide

At this time every day we have a 15-minute contractor site coordination/lookahead meeting. Everyone huddles around the 2-week lookahead whiteboard to discuss progress, future works, interface with other contractors, and other general site items. This meeting is very valuable to ensure work is progressing as planned and everyone is working together.

5.30 AM

No time to snooze the alarm; I have my morning routine down to the minute, so I can wake up as late as possible. 

6.40 AM

I get to the site at 6.40 am, sign in at security, and catch the site bus to the offices. I quickly fit in a bowl of cereal before the 7.00 am prestart meeting. At prestart, the supervisor runs through all the tasks, safety hazards, weather, and tides for today, so everyone is aware of what’s happening on site.

7.30 AM

It’s back to the offices, and I usually start my day by checking my emails and my calendar. I quickly check in with a subcontractor representative and then raise the required hold points/inspections for today with the client representative. 

8.30 AM

I head out to the site to check on progress. I take a lot of photos and monitor progress for our quality records. I also need to check that the concrete bin has been exchanged and monitor the site water usage.

Overlooking the water site

10.30 AM

My first meeting today is a weekly meeting with the client, a subcontractor representative, and a supplier representative. We have conducted some crane rail infill trials to determine the most suitable product; it needs to have a high compressive strength but also an element of elasticity. We are meeting to discuss material options following the infill trial and brainstorm pros and cons of the options trialed to date.

12.30 PM

Time for lunch! There isn’t a cafeteria on site, so lunch is last night’s left overs. When site isn’t too busy, we sit outside and have lunch together overlooking the wharf.

Overlooking the wharf  

1.00 PM

I have a hold point to ensure the crane rail is installed in accordance with the technical specification. I pop my head in next door to grab a subcontractor representative and our client representative, and we call for an escort to take us down to berth 2, where the rail installation is taking place.

A professional checking on the crane rail

2.30 PM

At this time every day we have a 15-minute contractor site coordination/lookahead meeting. Everyone huddles around the 2-week lookahead whiteboard to discuss progress, future works, interface with other contractors, and other general site items. This meeting is very valuable to ensure work is progressing as planned and everyone is working together.

3.00 PM

Mid-afternoon is usually when I am free to get some work done. Today I am compiling work-lots, closing out hold points, and sending out some emails.

An office desk with a PC and a laptop

4.30 PM

It’s time to plan for tomorrow’s work. I have to raise another permit for my work crew, and I also write a list of everything I want to accomplish tomorrow.

6.00 PM

I get home from work at approximately 6.00 pm, head off to the gym for 45 minutes, and then head back to my apartment to shower, cook and maybe watch a tv show before bed.